各种管道连接方式超级详细说明
PPR与PE管道连接
PPR and PE pipe connections
PE管道与PPR连接,黑色部分是PE变径弯头前面接PE管道,黄色的部分后接PPR管道
The PE pipe is connected to the PPR. The black section is the PE
variable bend. The front line is connected to the PE pipe. The yellow
section is connected to the PPR pipe
上图分解,黑色的配件为外螺纹直接,一边与PE热熔连接,一边螺纹连接
The above figure is broken. The black fittings are externally threaded,
one side with the PE hot melt connection, and the other with threaded
connections
阀门上方为PE管道DN50,下方为PPR管道,中间通过一个阀门连接,采用的配件均为两个外螺纹直接
Above the valve for the PE pipe DN50, PPR pipe below, in the middle
through a valve connection, the use of fittings are two external thread
directly
PE与法兰阀门连接,使用管径较大的管道连接,法兰两边可连接两种不同的管道,或同种管道
The PE is connected to a flanged valve and is joined by a pipe with a
larger diameter. The flanges can be joined to two different pipes or
pipes of the same kind
PE与UPVC管道连接,所用的配件与图2相似
The connection between the PE and the UPVC pipe is similar to the one shown in Figure 2
镀锌钢塑管与阀门连接
Galvanized steel plastic pipe and valve connection
上图局部放大,闸阀与止回阀连接
The local magnifying valve on the diagram is connected to the check valve
消防信号阀与DN150镀锌钢管连接
The fire signal valve is connected with DN150 galvanized steel pipe
水泵接合器与消防管道采用法兰连接
Flange connection with the pump adapter and fire pipeline
DN100的消火栓管用机械三通分支
DN100 fire hydrant pipe, mechanical three branches
机械四通,DN150主管两边接喷淋支管
Mechanical four way, DN150 main pipe on both sides of the spray pipe
消防管道中大于100的管道采用沟槽配件(卡箍)连接
More than 100 of the pipes in fire fighting pipes are connected by groove fittings (clamps)
消防管道的卡箍连接
Clamp connections for fire hose
对夹式蝶阀与消防管道采用法兰连接
Pairs of clip butterfly valve and fire pipe flange connection
铜管与阀门连接,铜管一般采用焊接
The copper tube is connected with the valve and the copper tube is welded in general
PE钢丝管网采用电容连接,图示电熔机
PE steel pipe network adopts capacitive connection
热熔机
Hot melt machine
彩铝檐沟管(铝管)属于金属管道,接口用承插打胶
Color aluminum tube (tube) belongs to the gutter metal pipeline interface socket glue
湿式报警阀连接
Wet alarm valve connection
水泵吸水管阀门连接
Water pump suction pipe valve connection
HPDE双壁波纹管
HPDE double wall corrugated pipe
HPDE双壁波纹管采用橡胶圈连接,留意橡胶圈
HPDE double wall bellows are made of rubber rings, and pay attention to rubber rings
下面是详细的说明
The following is a detailed description
1 管道丝扣连接(镀锌钢管、衬塑镀锌钢管)
Connecting 1 pipe threads (galvanized steel pipe, galvanized steel pipe with plastic lining)
1 断管:根据现场测绘草图,在选好的管材上画线,按线断管。
1 broken pipe: according to the site mapping draft, draw the line on the selected pipe, line broken pipe.
a 用砂轮锯断管,应将管材放在砂轮锯卡钳上,对准画线卡牢,进行断管。断管时压手柄用力要均匀,不要用力过猛,断管后要将管口断面的铁膜、毛刺清除干净。
A grinding wheel cutting pipe should be placed in the pipe wheel saw
calipers, alignment card draw off tube firmly. When the pipe is broken,
the handle of the handle should be uniform, not too hard, and the iron
film and burr of the pipe section should be removed after the pipe is
broken.
b 用手锯断管,应将管材固定在压力案的压力钳内,将锯条对准画线,双手推锯,锯条要保持与管的轴线垂直,推拉锯用力要均匀,锯口要锯到底,不许扭断或折断,以防管口断面变形。
B for hand broken pipe should be fixed on the pipe, pressure clamp
pressure case, blade alignment line drawing, push hands saw blade to
keep perpendicular to the axis of the tube, push tug force should be
uniform, saw to saw the end, do not wring or break, to prevent the pipe
section deformation.
2 套丝:将断好的管材,按管径尺寸分次套制丝扣,一般以管径15-32mm者套丝2次,40-50mm者套丝3次,70mm以上者套丝3-4次为宜。
2 sets of wire: the broken well pipe, according to the pipe size sub set
of threads, with diameter 15-32mm wire set 2 times, 3 times 40-50mm
sets of silk, more than 70mm sets of silk 3-4 advisable.
a 用套丝机套丝,将管材夹在套丝机卡盘上,留出适当长度将卡盘夹紧,对准板套号码,上好板牙,按管径对好刻度的适当位置,紧住固定扳机,将润滑剂管对准丝头,开机推板,待丝扣套到适当长度,轻轻松开扳机。
A threading machine set will be caught in the wire, pipe threading
machine chuck, set aside an appropriate length of the clamping plate
alignment, set number, good die, according to the proper position of the
dial diameter, tightly fixed trigger, the lubricant tube at the screw
head, boot push plate, screw to be set to when the length, gently loosen
the trigger.
b
用手工套丝板套丝,先松开固定扳机,将套丝板板盘退到零度,按顺序号上好板牙,把板盘对准所需刻度,拧紧固定扳机,将管材放在压力案压力钳内,留出适当长度卡紧,将套丝板轻轻套入管材,使其松紧适度,而后两手推套丝板,带上2-3扣,再站到侧面扳套丝板,用力要均匀,待丝扣即将套成时,轻轻松开扳机,开机退板,保持丝扣应有锥度。
B hand threading plate set wire, loosen the fixed trigger, will set
screw plate plate to the zero order number on the good die plate at the
required scale, tighten the trigger, will put pressure on the pipe
pressure clamp case, set aside an appropriate length of clamping, the
threading plate gently set into the pipe, the elastic moderate, then
push hands threading plate, belt buckle 2-3, stand to the side pull
sleeve wire plate, the force should be uniform, to be a screw, gently
loosen the trigger, boot back plate, screw thread taper should be
maintained.
3 配装管件:根据现场测绘草图将已套好丝扣的管材,配装管件。
3 equipped with fittings: according to the site will have a good sketch mapping thread pipe, pipe fittings.
a 配装管件时应将所需管件带入管丝扣,试试松紧度(一般用手带入3扣为宜),在丝扣处涂铅油、缠麻后带入管件,然后用管钳将管件拧紧,使丝扣外露2-3扣,去掉麻头,擦净铅油,编号放到适当位置等待调直。
A equipped with fittings should be required for fitting into the pipe
threads, try the tightness (usually by hand into the 3 button is
appropriate), in the thread apply lead oil, hemp after wrapping into
pipe, and then tighten the threaded pipe with a pipe wrench, exposed 2-3
buckle, remove hemp head, wipe the oil into the lead, No. the
appropriate place to wait for straightening.
b 根据配装管件的管径的大小选用适当的管钳
According to a B pipe diameter size appropriate pipe wrench
4.管段调直:将已装好管件的管段,在安装前进行调直。
4. pipe straightening: pipe fittings will be installed, before the installation of straightening.
a 在装好管件的管段丝扣处涂铅油,联接两段或数段,联接时不能只顾预留口方向而要照顾到管材的弯曲度,相互找正后再将预留口方向转到合适部位并保持正直。
A pipe thread fittings installed in place with lead oil, connecting two
or several, is not only to take care of the reserved hole direction of
pipe bending, find each other is after the direction of the mouth will
be reserved to the appropriate site and maintain integrity.
b 管段联接后,调直前必须按设计图纸核对其管径、预留口方向、变径部位是否正确。
B pipe connection, it must be adjusted according to the design drawings,
check the diameter of reserved opening direction, diameter changeable
parts are correct.
c 管段调直要放在调管架上或调管平台上,一般两人操作为宜,一人在管段端头目测,一人在弯曲处用手锤敲打,边敲打,边观测,直至调直管段无弯曲为止,并在两管段联接点处标明印记,卸下一段或数段,再接上另一段或数段直至调完为止。
C pipe straightening should be put in the diversion pipe rack or tube
platform, two general operation is appropriate, a person in the head of
Guan Duanduan visual, one in bend with the hand hammer, side beat,
observation, until the transfer pipe without bending, and marked the two
mark on the pipe connection point at the unloading period or periods,
followed by a period or periods of adjustment until the end.
d 对于管段联接点处的弯曲过死或直径较大的管道可采用烘炉或气焊加热到600-800℃(火红色)时,放在管架上将管道不停的转动,利用管道自重使其平直,或用木版垫在加热处用锤轻击调直,调直后在冷却前要不停的转动,等温度将到适当时在加热处涂抹机油。
D for pipe section at the connection point of the bending die or larger
diameter pipe can be heated to 600-800 DEG C oven or gas welding (red),
placed in the non-stop pipe rack pipe, the use of straight pipe weight,
or by heating with wood pad in the hammer tap straightening,
straightening after cooling before keep turning, such as temperature to
oil painting in the heating position when appropriate.
凡是经过加热调直的丝扣,必须标号印记,卸下来重新涂铅油缠麻,再将管段对准印记拧紧。
After all the heating straightening the threads, must label mark, down
to lead oil coated fiber winding pipe segment, and then tighten the
alignment mark.
e 配装好阀门的管段,调直时应先将阀门盖卸下来,将阀门处垫实再敲打,以防震裂阀体。
E fitted with the valve pipe section, straightening should first remove
the valve cover, the valve will be solid and then beat to the anti
cracking valve body.
f 镀锌碳素钢管不允许用加热法调直。
F galvanized carbon steel pipe is not allowed to be straightened by heating method.
g 管段调直时不允许损坏管段。
G pipe segments are not allowed to damage the pipe during straightening.
2 管道法兰连接(需要拆卸、与设备阀门等连接)
2 pipe flange connections (need to be removed, connected to equipment, valves, etc.)
2.1 凡管段与管段采用法兰盘联接或管段与法兰阀门连接者,必须按照设计要
2.1 where the pipe section and pipe section using flange connection or
pipe section and flange valve connection, must be in accordance with the
design